Skip to main content
ExplainerGrid ReliabilityExplainer· 5 min read· in Energy

The Missing Money Problem: How Capacity Markets Compensate Power Plants for Standby Reliability

The transition to intermittent renewable energy has exacerbated a structural flaw in wholesale electricity markets, forcing grid operators to pay generators billions annually simply to remain available during peak demand.

By Hao Li

Capacity Market Advocates 35%Energy-Only Proponents 35%Market Economists 30%
Capacity Market Advocates
Argue that forward capacity payments are the only reliable way to guarantee resource adequacy.
Energy-Only Proponents
Argue that allowing spot prices to rise during scarcity is the most efficient way to incentivize generation.
Market Economists
Analyze the structural flaws of both models and the distorting effect of price caps.

Perspectives this story doesn't cover

  • Consumer advocacy groups facing higher utility bills
  • Renewable energy developers navigating interconnection queues

At a glance

  • The 'missing money problem' occurs when price caps prevent power plants from recovering fixed costs during scarcity events.
  • PJM's 2026/2027 capacity auction cleared at a record $329.17 per megawatt-day, costing ratepayers an estimated $17.57 billion.
  • Energy-only markets like ERCOT avoid capacity payments but expose consumers to extreme price spikes up to $5,000 per megawatt-hour.
  • Surging data center load and retiring fossil fuel plants are currently stressing both market designs.

Why it matters now

Wholesale electricity market design dictates how billions of dollars in grid infrastructure are financed. Whether a region uses a capacity market or an energy-only framework directly determines the size of the reliability charge on every consumer's utility bill and the physical risk of rolling blackouts during extreme weather.

The transition to intermittent renewable energy and the surge in data center load have fundamentally altered how wholesale electricity markets value standby power, forcing grid operators across the United States to pay generators billions of dollars annually simply to exist. In the PJM Interconnection, which serves 65 million people from New Jersey to Illinois, the cost of this standby reliability has skyrocketed. For the 2026/2027 delivery year, the grid operator will pay power plants a record $329.17 per megawatt-day just to remain available for dispatch, a nearly 1,100 percent increase from the prices seen two years prior.[3]

This massive capital outlay is the direct result of a structural flaw in deregulated electricity grids known to economists as the "missing money problem." When wholesale electricity markets were designed in the late 1990s, the theory was that power plants would recover their fixed construction and maintenance costs by selling electricity during periods of high demand, when prices naturally spike. However, to protect consumers from extreme volatility, regulators imposed price caps on these spot markets.[1]

By artificially suppressing the price of electricity during scarcity events, those caps prevent generators—particularly natural gas "peaker" plants that only run a few hundred hours a year—from earning enough revenue to survive. As Cambridge University Press research outlines, "The missing money problem is a theory contending that features specific to electricity markets distort incentives for investment in generation capacity, impairing reliability." The money they need to remain economically viable is "missing" from the energy market. Without an alternative revenue stream, these critical backup plants retire, and developers refuse to build new ones.[1]

Price caps in wholesale energy markets prevent peaker plants from recovering their fixed costs, creating the missing money problem.

The problem is compounded by the zero-marginal-cost nature of renewable energy. When wind and solar farms generate electricity, they bid into the wholesale market at or near zero, driving down the average spot price of energy across the board. This "merit order effect" further erodes the energy-market revenues of traditional thermal plants, making them even more dependent on scarcity pricing just as regulators act to cap it.[1][4]

To solve this, grid operators like PJM created forward capacity markets. In these markets, the product being bought and sold is not electricity itself, but the promise to deliver it if called upon three years in the future. PJM determines how much total power the grid will need during the hottest hour of the summer, adds a reserve margin for safety, and holds an auction to procure that exact amount of capacity.[4]

To solve this, grid operators like PJM created forward capacity markets.

The financial scale of this mechanism is vast. For the 2026/2027 delivery year, PJM procured 146,244 megawatts of unforced capacity. At the clearing price of $329.17 per megawatt-day, Factlen calculates that the total cost of this capacity market will reach approximately $17.57 billion for the year. That cost is passed directly to utility customers as a reliability charge on their monthly bills, regardless of whether those specific power plants are ever actually turned on.[3][4]

PJM's capacity clearing price has surged nearly 1,100 percent in two years as load growth outpaces new generation.

The alternative to this system is the "energy-only" market, most prominently utilized by the Electric Reliability Council of Texas (ERCOT). ERCOT does not pay generators for capacity. Instead, it allows wholesale electricity prices to rise as high as $5,000 per megawatt-hour during grid emergencies. The promise of capturing those massive, fleeting windfalls is meant to be the sole financial incentive for developers to build and maintain power plants in the state.[2][4]

Energy-only markets theoretically avoid the missing money problem by refusing to cap prices below the true value of scarcity. However, they introduce immense political and operational volatility. When a winter storm or summer heatwave pushes the grid to the brink, the resulting price spikes transfer billions of dollars from consumers to generators in a matter of days, triggering intense political backlash and subsequent regulatory intervention.[1][2]

Both models are currently under severe stress from the dual pressures of retiring fossil fuel plants and surging demand from artificial intelligence data centers. In PJM, even the maximum allowable capacity price of $329.17 failed to attract enough supply to meet the grid's target, resulting in a 6.6-gigawatt shortfall. As analysts at Amperon note, "Power plants take longer to build than data centers—and markets have been ill equipped to handle that fundamental mismatch."[3]

Grid operators must balance the cost of capacity payments against the physical risk of rolling blackouts.

Meanwhile, the energy-only model faces its own reliability anxieties. ERCOT's May 2025 Capacity, Demand and Reserves report projects that the state's summer reserve margin will drop to 17.2 percent in 2026 and could fall to 9.0 percent by 2027 under certain load-growth scenarios. Because ERCOT relies entirely on the threat of scarcity to incentivize building, the grid must perpetually operate near the edge of a shortfall to function as designed.[2]

The missing money problem represents a fundamental debate over who bears the risk of keeping the lights on. Capacity markets force ratepayers to buy an expensive insurance policy upfront, guaranteeing that steel is in the ground but risking billions in over-procurement. Energy-only markets save consumers that upfront premium, but expose them to extreme price shocks and a higher physical risk of grid failure when the margins run thin.[1][4]

As load growth accelerates for the first time in two decades, the tension between these two frameworks is dictating the pace of the energy transition. Regulators are increasingly intervening in both models—adjusting price caps, tweaking load forecasts, and altering how intermittent wind and solar are credited for reliability. Until a market design emerges that can adequately value both clean energy and dispatchable backup power, the cost of grid insurance will continue to rise.[1][3]

Terms to know

Missing Money Problem
The revenue shortfall created when regulatory price caps prevent power plants from recovering their fixed costs during periods of high electricity demand.
Capacity Market
A forward market where grid operators pay power plants for the promise to be available to generate electricity during future peak demand periods.
Energy-Only Market
A wholesale electricity market that relies entirely on high spot prices during scarcity events to incentivize the construction of new power plants, without offering capacity payments.
Unforced Capacity (UCAP)
A power plant's maximum generation output adjusted downward to account for its historical forced outage rate, representing the actual reliable power it can provide.
Reserve Margin
The amount of backup generation capacity a grid maintains above its forecasted peak demand to protect against unexpected plant failures or extreme weather.
Peaker Plant
A power plant, typically powered by natural gas, that only runs during the few hundred hours a year when electricity demand is at its absolute highest.

Questions readers ask

What is the missing money problem?

It is an economic theory explaining that regulatory price caps in wholesale electricity markets prevent power plants from earning enough revenue during scarcity events to cover their fixed costs, leading to underinvestment in new generation.

How do capacity markets work?

Grid operators forecast future peak demand and hold an auction to pay power plants a fixed daily rate simply to remain available for dispatch, providing them a guaranteed revenue stream independent of the electricity they actually generate.

What is an energy-only market?

A market design, like ERCOT in Texas, that does not pay generators for capacity. Instead, it allows wholesale electricity prices to spike to extreme levels during emergencies, using the promise of those windfalls to incentivize developers to build power plants.

Why are capacity prices rising in PJM?

A combination of retiring fossil fuel plants, surging electricity demand from data centers, and interconnection delays for new renewable projects has created a supply shortage, driving capacity prices to their regulatory caps.

Sources

Source coverage

4 outlets

3 viewpoints surfaced

Capacity Market Advocates 35%Energy-Only Proponents 35%Market Economists 30%
  1. [1]Cambridge University PressMarket Economists

    Reliability and the Missing Money Problem

    Read on Cambridge University Press
  2. [2]ERCOTEnergy-Only Proponents

    Capacity, Demand and Reserves Report

    Read on ERCOT
  3. [3]AmperonCapacity Market Advocates

    The 8-Fold Path of PJM's Capacity Prices

    Read on Amperon
  4. [4]Factlen Editorial TeamMarket Economists

    Synthesis by Factlen editorial team

    Read on Factlen Editorial Team

Comments

Stay informed

Every angle. Every day.

Get Energy stories with full source coverage and perspective breakdowns delivered to your inbox.