Skip to main content
Offshore WindExplainerAug 3, 2026, 7:58 PM· 3 min read

Dominion's 2.6 GW Offshore Wind Project Cost Jumps $300M Due to Grid Upgrades and Tariffs

The largest offshore wind farm in the United States is now 81% complete and generating power, but its final price tag has risen to $11.65 billion following grid interconnection revisions and new federal tariffs.

By Miguel Carvalho

Utility Developers 35%Grid Operators 25%Financial Analysts 25%Energy Journalists 15%
Utility Developers
Focuses on the long-term asset value, manufacturing milestones, and projected fuel savings of mega-projects.
Grid Operators
Prioritizes system reliability, transmission constraints, and strict cost allocation rules for new generation.
Financial Analysts
Evaluates project delays through the lens of ratepayer impact, capital discipline, and corporate earnings guidance.
Energy Journalists
Tracks the broader industry implications of tariffs, supply chain bottlenecks, and regulatory hurdles.

Why this matters

As the United States attempts to decarbonize its grid, the Coastal Virginia Offshore Wind project serves as the ultimate test case for mega-project execution. Its ability to absorb hundreds of millions in tariff and grid-upgrade costs while still delivering power proves that the transition is physically viable, even if the final miles are expensive.

Key points

  • Dominion Energy's Coastal Virginia Offshore Wind project is currently 81% complete.
  • The total project budget has increased by roughly $288 million to $11.65 billion.
  • The cost increase is driven by PJM grid upgrades, federal tariffs, and subsea installation challenges.
  • Final turbine installation has been delayed by six months to the end of 2027.
  • Despite the delays, 31 turbines are already installed and feeding over 450 megawatts to the grid.
$11.65B
Updated total project cost
$288M
Cost increase since Q1 2026
2.6 GW
Total planned power capacity
81%
Project completion status
>450 MW
Power currently feeding the grid

The Coastal Virginia Offshore Wind (CVOW) project is a historic piece of American engineering. Situated 28 miles off the coast of Virginia Beach, it is designed to be the largest offshore wind farm ever constructed in the United States.[5]

During its second-quarter 2026 earnings update, Dominion Energy revealed that the massive infrastructure project has reached an 81% completion milestone.[1]

However, the final stretch of construction will require more time and capital than previously projected. The total budget has increased by approximately $288 million, bringing the final estimated price tag to $11.65 billion.[1]

Furthermore, the installation of the 176th and final turbine has been pushed back by six months, with completion now targeted for the end of 2027.[1][3]

The project's budget has expanded by roughly 2.5% in the latest quarter, driven by grid upgrades and tariffs.
The project's budget has expanded by roughly 2.5% in the latest quarter, driven by grid upgrades and tariffs.

While a nearly $300 million cost increase sounds staggering in isolation, it represents a roughly 2.5% adjustment on a project of unprecedented scale.[1][3]

The budget revision is driven by three specific factors: complex onshore grid upgrades, recent federal trade tariffs, and the physical realities of operating heavy machinery on the Atlantic seafloor.

Connecting 2.6 gigawatts of new electricity to the mainland is not as simple as running a subsea cable to the beach. It requires extensive onshore infrastructure to safely absorb and route the power.[4]

This integration is overseen by PJM Interconnection, the regional transmission organization that coordinates the wholesale electricity grid across 13 states and Washington, D.C.[4][6]

When a massive new generation source like CVOW comes online, PJM mandates "network upgrades" to the broader grid to prevent transmission bottlenecks and ensure system reliability.[4][6]

Historically, the developers of new power plants bear a significant portion of these upgrade costs. During the second quarter, Dominion navigated a complex reallocation of these PJM-assigned liabilities, which contributed to the shifting budget.[1]

Historically, the developers of new power plants bear a significant portion of these upgrade costs.

The second major driver of the cost increase is international trade policy. In April 2026, the federal government imposed new tariffs on imported clean energy components.[1]

These tariffs added an estimated $228 million in unexpected costs to the CVOW budget.[1]

The mechanism of offshore wind integration involves multiple stages of high-voltage transmission, each vulnerable to supply chain and tariff pressures.
The mechanism of offshore wind integration involves multiple stages of high-voltage transmission, each vulnerable to supply chain and tariff pressures.

While Dominion is utilizing the Charybdis—the first Jones Act-compliant wind turbine installation vessel built by American shipyard workers in Texas—the broader offshore wind industry still relies heavily on global supply chains for specialized subsea cables and transition pieces.[5]

The third factor extending the project's timeline is the physical challenge of deep-ocean construction.[1][3]

Each turbine tower stands roughly as tall as a 38-story building and must be anchored to the seabed using a massive steel monopile foundation.[5]

Dominion reported that harder-than-expected subsea conditions at certain turbine locations required longer "jacking" durations—the process by which the installation vessel lifts itself above the waves on mechanical legs to provide a stable lifting platform.[1][3]

While final turbine installation will stretch into late 2027, the bulk of the project's heavy manufacturing is already complete.
While final turbine installation will stretch into late 2027, the bulk of the project's heavy manufacturing is already complete.

Pushing the final installation date to late 2027 also provides the project with a necessary weather contingency buffer, acknowledging the unpredictability of the Atlantic hurricane season.[1]

Despite the delays and budget adjustments, financial analysts and Dominion's leadership maintain that the project is now substantially de-risked.[1][3]

The theoretical risks of manufacturing are largely in the rearview mirror: 99% of the steel towers and 85% of the composite blades have already been fabricated.[1]

Most importantly, the project is already delivering on its core promise. As of August 2026, 31 turbines have been successfully installed, feeding more than 450 megawatts of clean electricity into the grid and providing tangible fuel savings for Virginia ratepayers.[1][3]

How we got here

  1. November 2021

    The original $9.8 billion project budget is submitted to the Virginia State Corporation Commission.

  2. January 2026

    The first Siemens Gamesa 14.7 MW turbine is installed by the Charybdis vessel.

  3. March 2026

    The Coastal Virginia Offshore Wind project sends its first commercial electricity to the grid.

  4. April 2026

    New federal tariffs are imposed on imported clean energy components, impacting the project's budget.

  5. July 2026

    Dominion announces an 81% completion milestone alongside a revised $11.65 billion budget.

  6. Late 2027

    The revised target date for the installation of the 176th and final turbine.

Viewpoints in depth

The Utility's View

Dominion Energy views the project as substantially de-risked despite the recent cost adjustments.

From the developer's perspective, a $288 million increase on an $11.65 billion budget is a manageable 2.5% variance, especially for a first-of-its-kind mega-project. Dominion's leadership emphasizes that the heaviest risks—manufacturing the massive components and proving the installation concept—have already been retired. With 81% of the project complete and 450 megawatts already generating revenue and fuel savings, the utility argues that the delayed timeline reflects prudent weather contingencies rather than systemic failure.

The Grid Operator's View

PJM Interconnection must ensure that adding 2.6 gigawatts of power does not destabilize the regional grid.

Regional transmission organizations like PJM operate under strict reliability mandates. When a massive influx of intermittent renewable energy is proposed, the existing onshore transmission lines and substations must be upgraded to handle the load. PJM's cost allocation rules are designed to ensure that the developers triggering these necessary network upgrades bear a proportionate share of the financial burden, protecting existing ratepayers from subsidizing corporate generation assets.

The Market Analyst's View

Financial markets are weighing the cost of delays against the utility's steady earnings guidance.

For market analysts, the six-month delay and $288 million cost bump are blemishes on an otherwise strong quarter. However, because Dominion has maintained its long-term earnings per share (EPS) guidance and successfully completed its equity financing programs, the market has largely priced in the delay. Analysts note that as long as the project continues to hit its revised installation targets and the cost-sharing agreements protect the utility's balance sheet, the long-term compounding value of the asset remains intact.

What we don't know

  • Whether the remaining 145 turbines will encounter further subsea jacking delays during installation.
  • How future shifts in federal trade policy might impact the cost of replacement parts or ongoing maintenance.
  • The exact final impact on Virginia residential utility bills once the project is fully amortized over its lifespan.

Key terms

PJM Interconnection
The regional transmission organization that coordinates the movement of wholesale electricity across 13 states and Washington, D.C.
Network Upgrades
Modifications to the broader electrical grid required to safely absorb and distribute power from a new generation source.
Monopile Foundation
A massive steel tube driven deep into the seabed to support an offshore wind turbine.
Jones Act
A federal law requiring that vessels transporting cargo between US ports be American-built, American-owned, and American-crewed.
Levelized Cost of Energy (LCOE)
A measure of the average net present cost of electricity generation for a plant over its entire lifetime.

Frequently asked

Why did the cost of the CVOW project increase?

The $288 million increase is driven by revised network upgrade costs assigned by PJM, recent federal tariffs on imported components, and a six-month extension for final turbine installation.

Is the wind farm already generating electricity?

Yes. As of August 2026, 31 turbines have been installed and are already feeding more than 450 megawatts of power into the grid.

Will this cost increase raise customer utility bills?

Dominion expects minimal impact on customer bills, noting that the project is still projected to deliver $5 billion in fuel savings over its first decade to offset capital costs.

What is the Charybdis?

The Charybdis is the first Jones Act-compliant wind turbine installation vessel, built by American shipyard workers in Texas specifically to construct offshore wind farms in US waters.

Sources

Source coverage

6 outlets

4 viewpoints surfaced

Utility Developers 35%Grid Operators 25%Financial Analysts 25%Energy Journalists 15%
  1. [1]Seeking AlphaFinancial Analysts

    Earnings Call Insights: Dominion Energy (D) Q2 2026

    Read on Seeking Alpha
  2. [2]Dominion EnergyUtility Developers

    Coastal Virginia Offshore Wind Project Updates

    Read on Dominion Energy
  3. [3]TIKRFinancial Analysts

    TIKR Values Dominion Energy Stock at $94, Pricing In a Utility Compounding Through Its Wind Delay

    Read on TIKR
  4. [4]PJM InterconnectionGrid Operators

    PJM Project Status and Cost Allocation

    Read on PJM Interconnection
  5. [5]DredgeWireUtility Developers

    Coastal Virginia Offshore Wind project sends first electricity to the grid

    Read on DredgeWire
  6. [6]Zero Emission GridGrid Operators

    PJM Interconnection Reforms and Cost Allocation Rules

    Read on Zero Emission Grid
Stay informed

Every angle. Every day.

Get energy stories with full source coverage and perspective breakdowns delivered to your inbox.