AI InfrastructureLegal Challenge· 4 min read· in Community

Georgia Citizens Sue County Over Secret Zoning Change for $20 Billion OpenAI Data Center

Three Effingham County residents have filed a lawsuit challenging a recent zoning ordinance that cleared the way for a massive artificial intelligence data center, alleging officials bypassed required public hearings.

By Kavya Nair

Transparency Advocates 40%Economic Development Officials 30%Technology Infrastructure Planners 30%
Transparency Advocates
Argue that local governments must follow established zoning procedures and prioritize public input over corporate secrecy.
Economic Development Officials
Focus on the historic economic benefits and tax revenue generated by securing a massive technology investment.
Technology Infrastructure Planners
View the dispute as a predictable friction point in the rapid physical expansion of the artificial intelligence industry.

Perspectives this story doesn't cover

  • OpenAI Corporate Leadership
  • Georgia Power Grid Operators

Why this matters

For communities nationwide facing a surge in artificial intelligence infrastructure, this lawsuit establishes that procedural shortcuts and corporate nondisclosure agreements carry severe legal risks. It demonstrates how local residents can use established zoning laws to force transparency and public debate on utility-intensive mega-projects.

Key points

  • Three Effingham County residents filed a lawsuit to invalidate a zoning ordinance that cleared the way for a $20 billion OpenAI data center.
  • The complaint alleges county commissioners bypassed required public hearings and expanded land-use definitions behind closed doors.
  • The lawsuit targets the procedural approval process rather than explicitly seeking to ban the 1,400-acre artificial intelligence facility.
  • The project, known as Project Camellia, would require up to 3.2 gigawatts of electricity and make OpenAI the county's largest taxpayer.

The binding constraint on a $20 billion hyperscale artificial intelligence data center is the local zoning code that permits it to be built, and in Effingham County, Georgia, that legal foundation is now under judicial review. Three local residents filed a comprehensive lawsuit on September 2 challenging Ordinance 2026-352, the specific zoning amendment that cleared the way for OpenAI's massive 1,400-acre "Project Camellia." For local governments negotiating mega-projects, the legal risk of procedural shortcuts is now on full display: the plaintiffs allege that county commissioners deliberately bypassed required public hearings and rewrote land-use definitions behind closed doors, violating both the Georgia Zoning Procedures Law and their own local ordinances.[3][5]

The lawsuit does not seek to ban artificial intelligence development outright or explicitly halt the construction of the data center itself. Instead, it surgically targets the procedural mechanics of how the county expanded its permitted-use table to allow hyperscale data centers on industrially zoned property without requiring case-by-case conditions or community input. The three residents—Dr. Michelle Finch-Mincey, Lehman Mincey Jr., and Raymond Carver—filed a 14-page complaint accompanied by 300 pages of exhibits. They are asking a Superior Court judge to invalidate the ordinance entirely and formally enjoin the county from acting on it until all mandated public hearing requirements are met.[1][3][5]

At the center of the legal dispute is a multi-month negotiation process that residents say was intentionally shielded from public view to prevent organized opposition. According to the complaint, the Effingham County Board of Commissioners appointed an unpermitted Development Services Steering Committee in December 2024 to review proposed zoning changes. The lawsuit alleges this committee had no actual authority under the existing zoning ordinance to review or recommend those changes. Nevertheless, the group met repeatedly between December 2024 and August 2025 as part of an "Effingham County Ordinance Rewrite," during which the county expanded its land-use definitions from 93 to over 550, formally adding data centers to the approved list.[3]

Project Camellia represents a massive infrastructural footprint, requiring up to 3.2 gigawatts of electricity.

The plaintiffs contend that the county's own established zoning rules strictly require two separate public hearings—one before the Planning Board and a second before the County Commission—before any zoning change can legally take effect. According to the lawsuit, neither of these mandatory hearings occurred before commissioners gave the ordinance final approval on August 4, 2026. "We filed the suit not necessarily to attack AI in general, but we filed it to attack the process here, because the people deserve transparency in their government actions," said Greg Gilluly, a former federal prosecutor and the Savannah-based attorney representing the residents.[1][3][5]

According to the lawsuit, neither of these mandatory hearings occurred before commissioners gave the ordinance final approval on August 4, 2026.

The economic and infrastructural stakes for OpenAI are massive, making the zoning dispute a critical bottleneck for the technology company. Project Camellia represents a 15-year, $20 billion capital investment that would instantly make the artificial intelligence firm the largest taxpayer in Effingham County and the single largest electricity customer in the state of Georgia. The hyperscale facility is projected to require up to 3.2 gigawatts of electricity—enough power to supply roughly three cities the size of Atlanta—alongside millions of gallons of water daily for its advanced liquid cooling systems.[1][5]

The complaint also brings the county's private negotiations over Project Camellia directly into the zoning dispute, highlighting a strict nondisclosure agreement signed by County Manager Tim Callanan and OpenAI OpCo, LLC. The suit alleges this corporate agreement explicitly prohibited Callanan from sharing any information concerning the project with the public, including the local taxpayers who fund his salary. The plaintiffs argue that this arrangement fundamentally subverts democratic oversight. "Government power should come from the consent of the people, not multi-billion-dollar corporations having secret meetings with public officials," the lawsuit states, framing the zoning change as the culmination of a multi-year scheme to hide the project's details.[3]

The lawsuit alleges the county expanded its permitted-use definitions from 93 to over 550 without the required public hearings.

Effingham County officials have not yet filed a formal legal response in Superior Court to address the allegations. A county spokesperson stated in an email that the Board of Commissioners maintains a strict policy of not commenting on pending or ongoing litigation. The presiding judge will shortly set the timeline for the county's legal response, which will determine whether the current zoning ordinance stands or if the county must completely restart the approval process in full public view, potentially delaying the data center's construction timeline.[1][5]

For communities nationwide facing a sudden surge in hyperscale data center proposals, the Effingham County lawsuit serves as a highly visible procedural test case. It establishes that while local governments may be eager to secure historic tax revenues and unprecedented economic development deals, the legal mechanisms used to accommodate those projects must survive intense public scrutiny and strict adherence to established zoning laws. If the residents succeed in invalidating the ordinance, it will force municipalities to prioritize transparency over corporate nondisclosure agreements when negotiating utility-intensive infrastructure.[1][3]

Sources

Source coverage

5 outlets

3 viewpoints surfaced

Transparency Advocates 40%Economic Development Officials 30%Technology Infrastructure Planners 30%
  1. [1]The Current GATransparency Advocates

    Citizen-led lawsuit challenges zoning for OpenAI Georgia data center

    Read on The Current GA
  2. [2]WABETechnology Infrastructure Planners

    Citizen-led lawsuit challenges zoning for OpenAI Georgia data center

    Read on WABE
  3. [3]The Georgia VirtueTransparency Advocates

    Effingham County Residents Sue Over Zoning Ordinance That Paved Way for Data Center

    Read on The Georgia Virtue
  4. [4]WTOCTransparency Advocates

    Effingham County residents sue county over data center zoning ordinance, demand transparency

    Read on WTOC
  5. [5]Effingham HeraldEconomic Development Officials

    Effingham County Residents Sue Over Data Center Zoning Change

    Read on Effingham Herald