PJM Proposes Curtailing Power to New AI Data Centers During Grid Emergencies

The largest U.S. grid operator has asked federal regulators for the authority to cut power to large data centers during capacity shortages starting in 2027. The proposal aims to protect residential reliability as AI-driven electricity demand outpaces new generation.

By Miguel Carvalho

Grid Operators & Regulators 40%Data Center Developers 35%Environmental Advocates 25%
Grid Operators & Regulators
Prioritizing system-wide reliability and protecting residential consumers from the costs of AI expansion.
Data Center Developers
Emphasizing the need for continuous uptime and faster grid interconnection to maintain U.S. leadership in AI.
Environmental Advocates
Raising alarms about the localized pollution caused by industrial diesel backup generators.

Why this matters

As artificial intelligence models grow, their massive electricity requirements are beginning to compete directly with residential power needs. This policy shift means the tech industry can no longer assume unlimited grid access, forcing cloud providers to either build their own power plants or accept service interruptions that could affect enterprise software and AI tools worldwide.

Key points

  • PJM Interconnection has proposed a new rule to curtail power to large data centers during grid emergencies starting in June 2027.
  • The policy applies to new facilities drawing 50 megawatts or more that fail to secure their own independent power supplies.
  • Unhedged data centers would be forced onto backup generators before the grid operator asks residential customers to conserve power.
  • The proposal responds to a forecasted 70-gigawatt increase in large load demand by 2038, colliding with the retirement of older power plants.
50 MW
Threshold for 'Large Load' designation
67 million
People served by the PJM grid
70 GW
Projected large load growth by 2038
6,831 MW
Target for new capacity backstop auction
15 GW
PJM generation retired since 2022

The artificial intelligence boom has a physical footprint, and it is colliding with the hard limits of the American electrical grid. PJM Interconnection, the operator of the largest wholesale electricity market in the United States, has directed its staff to file a landmark proposal with federal regulators to manage the strain.[1]

PJM manages the flow of power for 67 million people across 13 states and the District of Columbia, a territory that includes Northern Virginia—the world's densest concentration of hyperscale data centers. As these facilities expand to train and run massive AI models, their power requirements are threatening to outpace the grid's ability to supply them.[2][3]

To protect residential and commercial customers from rolling blackouts, PJM's board of managers has approved a framework called the Interim Resource Adequacy Service. If approved by the Federal Energy Regulatory Commission, the policy will fundamentally change how the grid treats major computing loads starting in June 2027.[1][4]

The proposal establishes a strict "bring your own power" mandate for new, massive energy consumers. Any new facility drawing 50 megawatts or more—a threshold that captures virtually every modern AI data center campus—must prove it has secured sufficient independent or contracted power supplies.[2][6]

PJM faces a growing gap between forecasted electricity demand and available power generation.
PJM faces a growing gap between forecasted electricity demand and available power generation.

If a 50-megawatt facility fails to secure its own capacity, its electricity access becomes conditional. During a grid emergency, PJM will order these unhedged data centers to drop offline before it asks residential customers to conserve power or initiates rolling blackouts.[1][4]

This represents a two-tier reliability structure. Historically, grid operators have used Pre-Emergency Load Management—paying various industrial customers to voluntarily reduce consumption—as their first line of defense. Under the new rules, unhedged data centers will bear the first-mover risk, facing mandatory curtailment before those broader emergency measures are deployed.[4]

The mechanism of curtailment does not mean grid operators will casually switch off servers without warning. Affected data centers would be compensated for reducing demand, similar to existing demand-response initiatives. Facilities would typically receive an emergency signal and have roughly 15 minutes to transfer their operations to on-site backup power.[5][7]

The mechanism of curtailment does not mean grid operators will casually switch off servers without warning.

For most data centers, that backup power comes from industrial diesel generators. While diesel is easy to source and store locally, it introduces significant environmental friction. Federal rules generally limit these generators to 50 hours of operation per year for demand-response programs, and local communities have increasingly pushed back against the localized air pollution they create.[5][7]

PJM's aggressive regulatory posture is driven by stark grid mathematics. The operator forecasts that new large loads will add approximately 70 gigawatts of demand to its system by 2038. Simultaneously, the grid is losing its older, baseload power sources; roughly 15 gigawatts of generation, primarily coal and older natural gas plants, has retired across the PJM footprint since 2022.[2][6]

The grid operator is launching a specialized auction to secure over 6,800 megawatts of new supply.
The grid operator is launching a specialized auction to secure over 6,800 megawatts of new supply.

This divergence between surging demand and retiring supply culminated in PJM's most recent capacity auctions, which failed to secure the system's required 20 percent reserve margin. To fix the immediate shortfall, PJM's board approved a second measure: a Reliability Backstop Procurement.[1][5]

The backstop mechanism will launch a specialized central capacity auction in September and October 2026, targeting 6,831 megawatts of new supply. To incentivize rapid construction, PJM is offering a price ceiling of $555 per megawatt-day and allowing selected power plants to lock in commitments for up to 15 years, provided they come online by 2032.[1][4]

The threat of data center curtailment is not purely theoretical. During severe heat waves in May and July of 2026, the U.S. Department of Energy granted PJM emergency authority to force data centers onto backup generators if necessary to prevent wider grid failures.[7][8]

On July 2, 2026, as peak demand approached an all-time record of 166,147 megawatts, PJM issued an emergency warning to utilities to prepare for the possible curtailment of data centers in Maryland and Virginia. While the grid stabilized and the final step was not needed, the event proved that data centers are now firmly inside the grid's emergency playbook.[7][8]

Under the proposal, unhedged data centers would be curtailed before residential conservation measures are deployed.
Under the proposal, unhedged data centers would be curtailed before residential conservation measures are deployed.

For the technology sector, the implications are profound. Cloud computing contracts are built around guarantees of continuous uptime and availability zones. PJM's policy signals that computing capacity can now only grow as fast as the physical power system can support it, unless tech companies are willing to accept interruptions.[8]

The June 2027 effective date gives data center operators a narrow window to adapt. Facilities must now decide which workloads can be paused or shifted to other regions during a power crunch, and developers are increasingly looking to fund their own dedicated power sources, such as advanced geothermal or small modular nuclear reactors, to guarantee their AI ambitions are not unplugged.[4][8]

How we got here

  1. 2022–2026

    Approximately 15 gigawatts of older coal and natural gas generation retires across the PJM footprint.

  2. May 2026

    The Department of Energy grants PJM emergency authority to curtail data centers during a spring heat wave and maintenance crunch.

  3. July 2, 2026

    PJM issues an emergency warning to utilities to prepare for data center curtailments as peak demand approaches an all-time record.

  4. July 27, 2026

    PJM's board directs staff to file the Interim Resource Adequacy Service and Reliability Backstop Procurement proposals with federal regulators.

  5. September 2026

    PJM plans to launch a centralized backstop auction to procure 6,831 MW of new capacity.

  6. June 1, 2027

    The proposed compliance deadline for new large loads to secure independent power or face mandatory curtailment during emergencies.

Viewpoints in depth

Grid Operators & Regulators

Prioritizing system-wide reliability and protecting residential consumers from the costs of AI expansion.

PJM and federal regulators argue that the grid's primary function is to serve the public reliably. They view the explosive, concentrated growth of hyperscale data centers as an unprecedented strain that threatens to destabilize the network for 67 million people. By forcing unhedged data centers to bear the first-mover risk during emergencies, operators aim to shield households from rolling blackouts and ensure that existing customers do not absorb the massive infrastructure costs required to support AI development.

Data Center Developers

Emphasizing the need for continuous uptime and faster grid interconnection to maintain U.S. leadership in AI.

Cloud providers and data center operators argue that artificial intelligence is a critical economic and national security priority that requires continuous, uninterrupted power. While they acknowledge the grid's constraints, they point out that interconnection queues for new power generation are severely backlogged, making it difficult to bring their own clean energy online quickly. They warn that making electricity access conditional could delay AI scaling, force workloads to other regions, and complicate the strict uptime guarantees they provide to enterprise clients.

Environmental Advocates

Raising alarms about the localized pollution caused by industrial diesel backup generators.

Environmental groups and local community advocates are highly critical of the reliance on backup generation to solve grid emergencies. They note that when data centers are curtailed from the main grid, they typically switch to massive diesel generators. Even if limited to 50 or 100 hours a year, the simultaneous activation of dozens of these generators in dense data center hubs like Northern Virginia can create severe, localized air pollution, leading to millions of dollars in health-related costs for surrounding neighborhoods.

What we don't know

  • Whether the Federal Energy Regulatory Commission (FERC) will approve the proposals without significant modifications.
  • How strictly local environmental regulators will enforce pollution limits on the diesel backup generators used during these curtailments.
  • To what extent this policy will drive cloud providers to relocate planned data centers outside of the PJM footprint.

Key terms

Curtailment
The deliberate reduction or disconnection of electricity delivery to a specific customer or region to maintain the stability of the broader power grid.
Hyperscale Data Center
A massive, highly efficient computing facility built by major cloud providers to support vast amounts of data processing and artificial intelligence workloads.
Capacity Auction
A market mechanism used by grid operators to pay power plants to guarantee they will be available to generate electricity several years in the future, ensuring long-term grid reliability.
Demand Response
A program where large electricity consumers are financially compensated for voluntarily reducing their power usage during periods of high grid stress.
Megawatt (MW)
A unit of electrical power. One megawatt is roughly enough to power 750 to 1,000 homes, though a single large data center can consume 50 to 100 megawatts continuously.

Frequently asked

What is PJM Interconnection?

PJM is the largest regional transmission organization in the United States, managing the wholesale electricity grid for 67 million people across 13 states and Washington, D.C.

Why are data centers facing power cuts?

The rapid expansion of AI data centers is drawing massive amounts of electricity, threatening to outpace the grid's available power generation. PJM is proposing to cut power to unhedged data centers during emergencies to prevent rolling blackouts for homes and businesses.

When would these power cuts happen?

Curtailments would only occur during severe grid emergencies, such as extreme heat waves, when demand exceeds available supply. The policy is proposed to take effect in June 2027.

Do data centers just turn off when curtailed?

No. Most large data centers are equipped with massive industrial backup generators, typically running on diesel, which can power the facility independently when disconnected from the main grid.

Sources

Source coverage

8 outlets

3 viewpoints surfaced

Grid Operators & Regulators 40%Data Center Developers 35%Environmental Advocates 25%
  1. [1]Utility DiveGrid Operators & Regulators

    PJM board proposes capacity auction, data center curtailment to address shortfalls

    Read on Utility Dive
  2. [2]Network WorldData Center Developers

    Largest US power grid operator proposes curtailing AI data centers during emergencies

    Read on Network World
  3. [3]TD WorldGrid Operators & Regulators

    PJM Board Directs FERC Filings to Mitigate Data Center Power Demand

    Read on TD World
  4. [4]MLQ.aiEnvironmental Advocates

    PJM Board Orders FERC Filing to Curtail Data Centers That Don't Self-Supply Capacity

    Read on MLQ.ai
  5. [5]Market BriefsEnvironmental Advocates

    PJM Interconnection to cut power to large data centers during shortages

    Read on Market Briefs
  6. [6]IT Infrastructure ReportData Center Developers

    PJM proposes curtailing electricity to new AI data centers during grid emergencies

    Read on IT Infrastructure Report
  7. [7]Electric ChoiceGrid Operators & Regulators

    PJM Emergency Orders: Heat Wave Threatens Record Electricity Demand

    Read on Electric Choice
  8. [8]StartupFortuneData Center Developers

    Grid operators are now treating power-hungry compute as flexible demand