Army Paid General Dynamics $533 Million for Artillery Plant That Never Produced a Single Shell
A new $533 million ammunition factory in Texas, intended to rapidly boost U.S. production of 155mm artillery shells, has failed to produce a single usable part in its first two years of operation. The failure, driven by a high-risk attempt to repurpose outdated machinery, has severely hindered the Pentagon's goals to replenish stockpiles depleted by the war in Ukraine.
- Pentagon Watchdogs
- Focuses on the lack of accountability and the waste of taxpayer funds on unproven equipment.
- Defense Industry Advocates
- Argues that wartime production surges inherently require high-risk gambles that sometimes fail.
- National Security Analysts
- Views the failure as a symptom of a fragile, overly consolidated defense supply chain.
Common questions
Why did the Army build the Mesquite plant?
The facility was commissioned to rapidly increase the production of 155mm artillery shells, aiming to replenish U.S. stockpiles depleted by the war in Ukraine and reach a national goal of 100,000 rounds per month.
What caused the factory to fail?
General Dynamics and its subcontractor attempted to repurpose outdated machinery designed for older shells to forge modern M795 casings. The equipment could not handle the required steel, leading to catastrophic machine failures, fires, and cracked parts.
Has the contractor been penalized?
No. According to government watchdogs, General Dynamics was not forced to return the $533 million, received additional progress payments, and has since been awarded billions in unrelated defense contracts.
The short answer
- The U.S. Army paid General Dynamics $533 million to build a Texas factory to produce 30,000 artillery shells per month.
- Two years after opening, the Mesquite facility has failed to produce a single usable 155mm shell casing.
- The failure stems from a high-risk attempt to repurpose outdated Turkish machinery to forge modern M795 shells.
- Factory conditions included robotic arms catching fire, dropped steel blocks, and machines cracking the metal casings.
- The Army halted most work at the plant in 2025 but has not penalized the contractor or recovered the funds.
- The bottleneck leaves the U.S. producing only 36,000 shells a month, far short of its 100,000-round goal.
There is a persistent assumption in Washington that the U.S. defense industrial base can seamlessly surge to wartime production simply by injecting enough capital into established prime contractors. The reality, exposed by a half-billion-dollar failure in Texas, is far more brittle.[1]
In May 2024, the Army and General Dynamics Ordnance and Tactical Systems opened a sprawling new ammunition facility in Mesquite, Texas. Funded by $533 million in emergency supplemental spending, the plant was designed to be the cornerstone of a national effort to replenish 155mm artillery stockpiles depleted by the war in Ukraine.[1][4]
The facility was contracted to forge 30,000 steel projectile bodies every month. This output was critical to the Pentagon's broader objective of ramping up U.S. artillery production from a pre-war baseline of 14,000 rounds a month to a massive 100,000 rounds by late 2025.[3][4]
Yet, more than two years after it opened, the Mesquite plant has not produced a single usable shell casing. A scathing Department of Defense Inspector General report, corroborated by a sweeping ProPublica investigation in August 2026, revealed that the facility's production lines remain completely paralyzed by catastrophic equipment failures.[1][2][4]
The root of the failure lies in a high-risk procurement gamble. Rather than purchasing modern manufacturing systems, General Dynamics and a Turkish subcontractor, Repkon, attempted to adapt outdated machinery salvaged from a discontinued production line. That older equipment was originally designed to forge the M107, a shorter-range shell made from different steel.[1][3]
The root of the failure lies in a high-risk procurement gamble.
When tasked with shaping the harder steel required for the modern M795 shell, the repurposed machinery violently rejected the process. Former workers described a chaotic factory floor where robotic arms regularly caught fire, 1,800-degree steel blocks were dropped from the air, and giant presses had to be beaten with sledgehammers to function.[1][2]
Instead of precisely stretching the steel into aerodynamic casings, the machines routinely cracked the metal beyond repair or mangled it into twisted shapes. The facility repeatedly failed its first article testing, a mandatory milestone to prove it could meet military specifications.[1][4]
Recognizing the insurmountable technical hurdles, the Army ordered a complete work stoppage on two of the plant's three production lines in August 2025. Despite blowing eight consecutive deadlines, the third line continued to operate into 2026 without ever yielding a battle-ready component.[1][4]
The financial fallout has drawn intense scrutiny from government watchdogs. Despite delivering zero usable parts, General Dynamics was never formally penalized. The company retained the $533 million, received an additional $26.3 million in progress payments in December 2025, and has since been awarded $2.5 billion in unrelated defense contracts.[1][2]
This localized failure has created a severe bottleneck in the broader U.S. munitions supply chain. Because the Texas plant was responsible solely for forging the hollow steel tubes, its failure means downstream Army facilities in Iowa and Arkansas have no casings to fill with explosives.[3]
Without the 30,000 shells per month from Mesquite, the U.S. Army is currently stuck producing roughly 36,000 rounds a month—falling 71% short of its production capacity goals. This shortfall directly impacts the Pentagon's ability to supply allied forces in Europe and maintain its own deterrence posture in the Middle East and the Indo-Pacific.[3][4]
The Mesquite debacle illustrates the systemic fragility of a consolidated defense industry. When a single point of failure in a hollow steel tube can derail a national security imperative, it forces a reckoning over how the military balances the urgent need for speed against the rigorous oversight required for unproven manufacturing gambles.[1][4]
Why it matters
The U.S. military's inability to rapidly scale up basic munitions production exposes a critical vulnerability in the defense industrial base. The failure of the Mesquite plant not only wastes half a billion taxpayer dollars but also leaves U.S. and allied forces with depleted stockpiles at a time of heightened global conflict.
Jargon, explained
- 155mm Artillery Shell
- The standard heavy artillery round used by the U.S. Army and NATO allies, consisting of a forged steel casing filled with explosives.
- M795
- The modern, longer-range variant of the 155mm shell currently used by the U.S. military, which requires specific steel tolerances to manufacture.
- First Article Test
- A critical milestone in defense contracting where a facility must prove it can produce a component that meets all military specifications before full-scale production begins.
- Defense Industrial Base
- The network of private corporations, government facilities, and supply chains that research, develop, and manufacture military weapons and equipment.
Sources
[1]ProPublicaPentagon WatchdogsFiasco in the Factory: Taxpayers Funded a $533 Million Artillery Plant That Made Nothing
Read on ProPublica →
[2]Government ExecutivePentagon WatchdogsThe Army gave General Dynamics $533M to build an artillery plant that produced nothing
Read on Government Executive →
[3]The War ZoneNational Security AnalystsNew $500M Artillery Shell Plant Failed To Produce Any 155mm Parts
Read on The War Zone →
[4]CBS NewsNational Security AnalystsDefense watchdog finds new 155mm artillery plant failed to produce parts in 2 Years Since It Was Built, Hindering Production Goals
Read on CBS News →
[5]Ground NewsNational Security AnalystsGeneral Dynamics Took $533 Million for an Artillery Plant That Made No Usable Shells
Read on Ground News →
Comments
Every angle. Every day.
Get defense security stories with full source coverage and perspective breakdowns delivered to your inbox.